APAPES – THALES grant #377289

Work Packages

Work Packages: WP1  WP2  WP3  WP4  WP5  WP6  WP7  WP8  WP9  WP10  WP11  WP12 Timetable

 

APAPES TIMETABLE (update Jan 2014)

 

Table I: Projected new delay-adjusted summary of timetable from 1/10/2011 to 31/12/2015 stretching over the 48 month proposal period.

The more than 10 months delay in the transfer of funds to the APAPES project account at ELKE (UoC) resulted in the overall project delays shown below. Work packages (WP) are listed.

 

Shaded Area Symbol Indications: 

Limited activity

 

Use of Machine Shop

   

Tests with ion beams from accelerator

 

Electron spectroscopy with ion beams

 

 

Title

 

Activities

 

Deliverables

 

 

Start

End

2011

2012

2013

2014

2015

  06/10/2011

 31/12/2015

d

a

b

c

d

a

b

c

d

a

b

c

d

a

b

c

d

 

 

Á. Design, Construction and Testing

 

01/01/12 - 30/06/14

WP1 - Beam line: Design, construction and testing

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 01/10/11

30/06/14

WP2 - Two ion beam strippers: Design, construction, testing and use

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 01/10/11

30/06/14

WP3 - Zero-degree Auger projectile spectroscopy: SIMION modeling and design of experimental apparatus

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 01/10/11

30/09/14

WP4 - Collision chamber: Connection to beam line and vacuum apparatus

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

01/12/12

28/02/14

WP5 - Differentially pumped gas cell: Implementation and testing

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

01/06/13

30/06/14

WP6 - Electronics and Data Acquisition (DAQ): General design,  purchase, implementation,  development and use

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

01/12/13

30/6/14

WP7 - Electron spectrometers: Preparation,  setup and operation

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

1/07/13

30/6/14

Â. Measurements

 

1/07/14 - 31/12/15

WP8 - Measurements of electron spectra using ions from the TANDEM accelerator

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

1/07/14

31/12/15

C. Results and Dissemination

 

1/07/14 - 31/12/15

WP9 - Analysis and presentation of new results

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

1/07/14

31/12/15

WP10 - Dissemination of new results

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

1/07/14

31/12/15

D. APAPES Management

 

1/10/11 - 31/12/15

WP11 Administration

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

1/10/11

31/12/15

WP12 Independent evaluation

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

1/10/15

31/10/15